Project: FedEx Office Fitout & Mail Sorting Facility, Sydney

Fedex Sorting Facility

Project: FedEx Office Fitout & Mail Sorting Facility, Sydney
Project Builder: FDC Construction & Fitout
Consulting Engineer: Aston Consulting
Client: FedEx
Mechanical Works:

  • All new supplementary mechanical system to suit the tenants fitout
  • Refurbishment of end-of-life base building system
  • CRAC units to new communications room
  • Warehouse ventilation

Project Description

The new FedEx facility is located in close vicinity to Sydney airport. This meant that all cranes to lift HVAC equipment into place required clearance by CAASA so as not to impede any flights. CAASA clearance takes an extended time to process, and the project was on tight timeframes.

Our innovative solution was to source a heavy duty helicopter to fly the key fan components into place. Helicopter delivery approval by CAASA provided faster timeframes that were within the project tolerance.

 