Project: 80 George St, Sydney

80 George St HVAC

Project: 80 George St, Sydney
Project Builder: Brisull Industries
Consulting Engineer: Norman, Disney & Young
Client: Sydney Harbour Foreshore Authority
Mechanical Works:

  • Replacement of all capital equipment
  • New Building Management System
  • Temporary chilled water system
  • New 800kw chiller plant
  • Boilers
  • Pumps
  • Risers
  • Replacement of localised air conditioning for retail tenants

Project Description

The Sydney Harbour Foreshore Authority undertook to reposition their building asset through an entire building upgrade.

Challenges included existing tenants remaining within the building whilst the entire building was occupied with a mix of commercial and retail tenants, requiring creative solutions to maintain air quality and air-conditioning during construction.

Careful project planning was required to maintain conditions to the retail and commercial tenants at all times during the works.

Replacement of localised air conditioning to a row of retail tenants needed to be completed within a 48-hour window. We successfully completed the changeover of the retail tenants in this time frame which included the following:

  • Removal of all existing HVAC systems
  • Installation of all new chilled / heating water fan coil units and associated systems
  • Cut over from end of life system to new
  • Tested, balanced and commissioned and ready for trade on Monday morning.
Share This